How a Utility-Scale Wind Turbine Is Built
1. Site Selection & Planning For A Wind Turbine
- Wind resource assessment: Measure wind speeds over 1–2 years using meteorological masts or LiDAR.
- Grid connection study: Ensure transmission lines can handle generated power.
- Environmental & social studies: Wildlife impact, noise, visual impact, local regulations.
- Land acquisition & permits: Work with local governments and landowners.
2. Design & Engineering
- Turbine size: Most modern turbines are 2–6 MW onshore and 8–15 MW offshore.
- Blade length: 40–120 meters (longer = more power, but harder to transport).
- Tower height: 80–150 meters for onshore; 100–200 meters offshore.
- Generator system:
- Direct drive (no gearbox, low maintenance).
- Gearbox drive (lighter generator, more complex).
3. Major Components
- Rotor Blades
- Made of fiberglass, carbon fiber, or composite materials.
- Manufactured in huge molds with resin infusion.
- Nacelle (the “box” at the top)
- Contains gearbox (if used), generator, cooling, yaw system, and control electronics.
- Tower
- Made of steel sections, bolted together on-site.
- Offshore: may use monopiles, jackets, or floating platforms.
- Hub
- Connects blades to the main shaft.
- Control system
- Monitors wind speed, direction, power output, safety shutdown.
4. Manufacturing Process
- Blades: Built in specialized blade factories. Each blade can weigh 10–50 tons.
- Towers: Fabricated in steel sections, transported by trucks or ships.
- Nacelle & Generator: Assembled in factories with heavy-duty machining.
5. Transportation & Logistics
- Blades, nacelles, and tower sections are oversized loads.
- Requires special trailers, ships (for offshore), and cranes.
- Route planning is critical (roads, bridges, tunnels).
6. Construction & Installation
- Foundation
- Onshore: Reinforced concrete base (can be 15–20 m diameter, 2–4 m deep).
- Offshore: Monopiles driven into seabed or floating platforms anchored with mooring lines.
- Tower erection
- Steel sections lifted and bolted together with massive cranes.
- Nacelle installation
- Lifted and secured on top of the tower.
- Blade installation
- Blades attached individually or as a pre-assembled rotor.
- Electrical connection
- Cables run down the tower to transformers and the grid.
7. Commissioning
- Turbine is tested for safety systems, yaw alignment, and electrical synchronization with the grid.
- SCADA (Supervisory Control and Data Acquisition) systems are set up for remote monitoring.
8. Operation & Maintenance
- Lifespan: ~20–25 years.
- Maintenance: Regular inspection, lubrication, gearbox/generator servicing.
- Repowering: After 15–20 years, blades or nacelle may be upgraded with new tech.
⚙️ Key Numbers for Modern Wind Farms
- Onshore turbine: 2–5 MW, 80–150 m tower, 100 m rotor diameter.
- Offshore turbine: 8–15 MW, 100–200 m tower, 150–240 m rotor diameter.
- Cost per turbine: ~$3–5 million (onshore), ~$10–20 million (offshore).
- Wind farm: Dozens to hundreds of turbines, connected to a substation.
👉 So in short: you don’t “build” one in a workshop — they’re manufactured in specialized global facilities (Siemens Gamesa, Vestas, GE, Goldwind, etc.) and then installed by engineering, procurement, and construction (EPC) teams with cranes, ships, and heavy equipment.